The crack sealing, Sealing and parking lot striping at Ballinger Point is being planned for the week of June 17th- June 21st.
June 17th (Mon.): The first section to be repaired will be the Upper Section, starting at the tennis courts and going down the drive lane half way. All residents who normally park there will have to either park on the Lower Section of the lot or park offsite.
June 18th (Tues): The Upper Section cannot be driven on or parked on for the day. Once again, All residents who normally park there will have to continue parking on the Lower Section of the lot or park offsite.
June 19th (Weds): The Lower Section will be repaired in the same manner. All residents who normally park there will have to either park on the Upper Section of the lot or park offsite.
June 20th (Thurs): The Lower Section cannot be driven on or parked on for the day. Once again, All residents who normally park there will have to continue parking on the Upper Section of the lot or park offsite.
June 21st (Fri): ALL CARS will need to be out of the lot to for the striping to be painted. Mind you, the cars parked in the garages will not have to be moved at all, but they will not be able to leave their garage either on that day.
When the week is through, we will have a wonderful parking lot! Thank you for your patience as the repairs get under way.